Description
Order of production
Main technical characterestics and list of basic equipment
Table 1
|
Useful capacity, kWatts (hp)
|
452 (615)
|
|
Mode of working
|
See table 2
|
|
Assembly base
|
|
- chassis type
|
KrAZ-63221-0000044
|
|
- engine power, kWatts (hp)
|
240 (330)
|
|
- load capacity, kg
|
22725
|
|
Power unit
|
|
- diesel engine
|
V2-800TK-S4
|
|
- aggregate capacity, kWatts (hp), not more than
|
588 (800)
|
|
- rotation frequency of crankshaft, rev/min, not more than:
|
|
|
?) under the aggregate capacity
|
2000
|
|
b) maximum
|
2300
|
|
- starting system
|
electric starter ST 722
|
|
- accumulator, 4 items
|
6??-190
|
|
Gear box
|
|
- type
|
3?Pm
|
|
- gear ratio:
|
|
|
a) at I gear
|
4,67
|
|
b) at II gear
|
3,43
|
|
c) at III gear
|
2,43
|
|
d) at IV gear
|
1,93
|
|
Pump
|
|
- type
|
3PN-70
|
|
- useful capacity, kWatts
|
452
|
|
- plungers, items
|
3
|
|
- plunger diameter, mm:
|
|
|
a) in delivered set
|
100
|
|
b) in spare set
|
120
|
|
- plunger stroke, mm
|
200
|
|
- gear ratio of power end
|
4,86
|
|
Rotary pump
|
|
- type
|
CNS 60-200
|
|
- shaft speed, rev/min
|
1475
|
|
- feed, m3/h
|
60
|
|
- maximum pressure, MPa (kgf/cm2)
|
2 (20)
|
|
- transmission
|
from chassis power takeoff
|
|
Measuring tank, m3
|
4
|
|
Manifold
|
|
- internal diameter of pipe line section, mm:
|
|
|
a) suction
|
100
|
|
b) discharge
|
50
|
|
Control of the unit
|
From chassis cabin
|
|
Auxiliary pipe line length, running meter, not more than:
|
|
- suction, 1 item
|
4
|
|
- discharge, 7 items
|
37 (total)
|
|
Auxiliary equipment
|
|
- cementing tank volume, m3
|
0,25
|
|
Total dimensions (L x B x H), mm, not more than:
|
11000?3910?2780
|
|
Weight, kg, not more than:
|
|
a) of equipped unit: chassis, attached implements (including chassis complement , accessories set, etc.), spare wheels*, fuel, lubricant, cooling systems filling)
|
26200
|
|
b) of attached implements unit
|
14200
|
|
c) of equipped chassis
|
12000
|
Table 2
Unit mode of working (rotation frequency of diesel crankshaft 1800 rev/ min)
|
Transmission
|
Total transmission ratio
(gear-box-pump)
|
Number of double
stroke of pump plunger,
a min.
|
Plunger d=100 mm
|
Plunger d=120 mm
|
|
Pressure, MPa
|
Feed, l/s
|
Pressure, MPa
|
Feed, l/s
|
|
I
|
22,60
|
80
|
70,0*
|
6,3
|
51,0*
|
9,0
|
|
II
|
16,55
|
109
|
54,0
|
8,5
|
37,5
|
12,3
|
|
III
|
11,80
|
153
|
38,0
|
12,0
|
26,6
|
17,3
|
|
IV
|
9,40
|
192
|
30,5
|
15,0
|
21,0
|
22,0
|
Notes
1 The value of FEED characteristic is calculated.
2 ATTENTION! After the first launching the rig should pass through 60-hours breaking-in. During the breaking-in the value of PRESSURE characteristic should not exceed 75 % of mentioned one. After the termination of the breaking-in you should discharge hot oil from the pump and gear-box, wash the oil reservoir and fill up with fresh oil.
3 * Overload capacity of discharge pressure in appropriate plunger diameter, at which the rig can operate for a short period of time.
The unit on-stream time at any regime is limited by the reheat temperature of oil in pump frame crankcase.
|